Question 3 OR (b) part 1

Matrix organisation

4 marks

Time to write
About 8 minutes

From an older CBCS paper

Question

Question 3 OR (b) part 1 · 4 marks

Write notes on: (1) Matrix Organisation

Reworded from the university paper; the task is the same. The original paper belongs to the University of Delhi. See DU's question bank.

Before you write

Read off the question and its marks

8 minfor 4 marks

Read from the question

  • notes onA note opens with the meaning, then two or three key points. No long introduction.

Write it in this order

  1. Read; underline the asks; jot your points 1 min
  2. 1 Meaning, with example 1 mark 2 min
  3. 2 Features 1 mark 2 min
  4. 3 Merits 1 mark 2 min
  5. 4 Limitations 1 mark 1 min

Easy marks

  • Step 1 opens with the meaning: a one-line definition, the quickest mark in it.

Try it first. About 8 minutes for 4 marks. Write it out, then open the solution.

Solution

Hover or tap a marked figure, like 72,000, to see how it is made and where else it appears.

Meaning

A matrix (or grid) organisation places a project structure over the permanent functional structure. Functional departments form the vertical lines of command and project teams the horizontal ones; where they cross, a matrix is formed, and members of a project team come under a dual line of command. It was developed for large, complex undertakings that need a structure more flexible and technically oriented than the line and staff or functional forms. An engineering firm in Hyderabad building a new metro signalling system might draw engineers, accountants and buyers from their departments into one project team for two years.

Picture itMatrix organisation

1Drawn from every department, the project team huddles over one drawing.

Project organisationThe team answers to the project manager rather than to the functional heads.

2Ajay at his desk, a file arriving from each side: the project boss and the department boss.

Matrix organisationThey therefore have two bosses.

Features

  • The project manager shares resources with the functional managers and does not have complete authority over them; in this it differs from a pure project organisation.
  • Staff are drawn from functional departments for a project and return to them for reassignment when it ends.
  • While on the project each member has two bosses, the functional head and the project head, so the authority of each must be clearly marked out.

Merits

  • Attention and resources are focused on each project, which helps planning, control and timely completion.
  • It is flexible: more projects can be taken up by forming more teams.
  • People learn new skills across projects, and direct contact improves communication and motivation.

Limitations

  • The double line of command confuses team members and breaks unity of command.
  • Members drawn from different departments may clash, and the project manager lacks line authority over them.
  • Functional heads find it hard to appraise staff spread over many projects, and two-way communication increases paper work and cost.

Where the 4 marks sit

#ComponentMarks
1Meaning, with example1
2Features1
3Merits1
4Limitations1
Total4
Keyboard: ← → previous and next question, / search

Report a problemopens an email to admin@getkunji.com with the question ID1205-Q3bOR1already filled in.