Question 2 OR (a) part ii

Music hall burnt before the concerts

3 marks

Time to write
About 6 minutes

From an older CBCS paper

Question

Question 2 OR (a) part ii · 3 marks
  1. For a series of concerts, C agreed to let out his musical hall to T. Before the date of the first concert, the hall was accidently brunt. T sued C, claiming damages for breach of contract. Is T able to recover damages for breach of contract ?

Reworded from the university paper; the task is the same. The original paper belongs to the University of Delhi. See DU's question bank.

Before you write

Read off the question and its marks

6 minfor 3 marks

Read from the question

  • Is T able…?A case problem: state the rule and its section, apply it to these facts, then answer in one line (yes or no, and why).

What the paper leaves open

Marked as one question of 9 marks; answered here in 3 parts of 3 marks each (marks inferred).

Write it in this order

  1. 1 (ii) The music hall 3 marks 6 min

Try it first. About 6 minutes for 3 marks. Write it out, then open the solution.

Solution

Hover or tap a marked figure, like 72,000, to see how it is made and where else it appears.

(ii) The music hall. A contract to do an act which, after it is made, becomes impossible by an event the promisor could not prevent becomes void when the act becomes impossible; destruction of the subject matter is a leading instance. The hall was accidentally burnt, without C's fault, before the first concert: the contract became void by supervening impossibility and both parties are discharged. T cannot recover damages for breach of contract.

Where the 3 marks sit

#ComponentMarks
1(ii) The music hall3
Total3